A decent start but I ran into a couple of issues. The splitter conveyor belts would only split the stream once and any split conveyors would not continue moving logs. A larger area to build in would also have been great.
Hi! Thanks for trying it out! Can you explain what you mean with the splitter? It seemed to work fine on my machine.
Maybe I was doing it wrong but I attached a beautiful drawing of how I had it set up.
The splitter would continue to use the middle lane but the top and bottom ones only received one log that would not move forward anymore
Thanks, I'll look into it maybe